Non-Revenue Water Reduction Projects
The objective of this assignment is to finalize standard template WSS operator’s procurement document for the Municipal Water Supply schemes including Standard Bid Document for the project. As part of this assignment, the consultant will investigate and recommend PPP design issues including mechanism of fund flow, O&M, and monitoring mechanism. DPHE has contracted a Technical Assistance consultancy to conduct Pre–feasibility, Feasibility and prepare the design and specifications, and the associated bidding documents for municipal towns’ piped water supply schemes.
Location & Country: | Dhaka and secondary cities, Bangladesh |
Name of Client: | The World Bank Group |
Duration of Assignment (months): | 6 |
Start Date (month/year): | June 2019 |
Completion Date (month/year): | September 2019 |
Professional Staff Months Provided: | 1 |
Names and designation of professional staff involved: | Anand K Jalakam, Team Leader |